Ninh Diem 3 Industrial Park
1. Information about the proposed project:
a. Project proposing investor : Sonadezi Khanh Hoa Joint Stock Company .
b. Project name: Investment in the construction and operation of infrastructure for Ninh Diem 3 Industrial Park .
c. Location of implementation: Dong Ninh Hoa ward and Bac Ninh Hoa commune , Khanh Hoa province.
d. Objective: To invest in the comprehensive construction of technical infrastructure in the industrial park and to lease or sublease land to investors for the construction of factories, offices, warehouses, service facilities, public utilities, and to implement investment projects, organize production, and conduct business in accordance with the law.
|
STT |
Operational objectives |
Industry codes according to |
CPC industry code |
|
1 |
Real estate business, |
6810 |
|
|
2 |
Construction of other civil engineering works |
4299 |
|
|
3 |
Water extraction, treatment, and supply |
3600 |
|
|
4 |
Drainage and wastewater treatment |
3700 |
|
|
5 |
Landscape care and maintenance services |
8130 |
|
e. Area: 288,839 hectares.
f. Total investment capital (excluding land clearance costs): VND 3,016.0 billion; land clearance costs approximately VND 628.577 billion).
g. Operating period: 50 years, starting from the date of the decision approving the investment policy.
h. Implementation schedule: no more than 36 months from the date the land is allocated by the state.
i. Method of investor selection: Bidding to select an investor, as two investors submitted valid applications for investment policy approval.